
Microsoft Project
Advanced

Saving the Baseline Plan
Creating a base line plan
Setting the baseline plan
Viewing the baseline statistics
Tracking Project Progress
Examining the Tracking Gantt chart
Formatting the current date line
Updating tasks that started & finished on schedule & tasks that finished late
Displaying progress lines
Updating the percent of duration complete
Updating the percent of work complete
Updating remaining work using the Task Usage view
Viewing progress in the PERT chart
Adjusting the Schedule
Splitting a task
Using Detail Gantt to view interim plans
Setting an interim baseline plan
Creating a Interim Gantt Chart
Risks & Issues
Working with Resources
Delaying resource work
Assigning overtime
Removing effort driven scheduling from a task
Managing Multiple Projects
Determining when to use a subproject
Inserting projects into the main project
Linking a predecessor to a successor within
consolidated projects
Assigning a high priority project
Sharing resources from another project
Updating and refreshing the resource pool
Levelling shared resources
Importing and Exporting Data
Importing resource information from Excel
Exporting task information to Excel
Customizing the Microsoft Project Environment
Copying Views and Tables